Construction progress of Vinhomes Ocean Park project: HVC Group meets the investor's requirements
01/11/2019
Starting receiving ground for deploying from the beginning of the first quarter of 2019 to perform the works of more than 20 contracts, HVC Group has completed many categories under the project, the remaining items are always ahead of schedule, meeting the requirements of The investor's demands on complexity, technical requirements, art and construction methods.
Vinhomes Ocean Park project is located in Trau Quy, Gia Lam, Hanoi, invested by Vingroup, is a complex of high-rise apartments, villas, commercial centers, auxiliary utilities. With a total area of the project of 420ha wide, expected scale of more than 60 towers from 25 to 38 floors. HVC Investment and Technology Joint Stock Company is the M&E contractor for the construction infrastructure and main roads in sections 2 and 4; high-rise m&e for buildings P2, S12; M&E of auxiliary areas; system of swimming pools and fountains. Especially, HVC Group provides technology and constructs automatic watering system, technology to treat artificial saltwater lake at the project .... It is expected that HVC Group will complete the works. As committed in 2020.
A corner of the Vinhomes Ocean Park project (current progress)
Mechanical and electrical infrastructure: always ready for meeting requirements from Vingroup
According to Mr. Nguyen Xuan Truong - commander of the construction site: With the assignments assigned by the investor, HVC has been executing speedy, right techniques, handing over any completed category, harmonize with the general progress of the whole project. Specifically:
Completing the M&E system for main roads D19, N3, D49, N11, N17 ...; N2, D6, D5 and NB01 routes of high-pressure lighting lamps, water lines eligible for connection with clean city water, ...
Some items have been completed 50% such as: Construction of infrastructure and landscape - M&E part - Landscape infrastructure CT2 + CT3 + CT04 PK2.
Many works are being actively implemented by HVC, waiting for the ground from the investor and expected to complete on schedule such as: M&E infrastructure construction (Electricity, water, fire protection, information, camera ...) zone 4 - low-rise; Construction of MEP including installation of technology equipment, Artwork, a boat of 24.5ha lake; ...
M&E contractor of high-rise buildings: exceeding the assigned schedule
In parallel with the completion of the Park 2 building, HVC Group rushed to execute the electromechanical part of the S12 building. With a team of skilled personnel, in just a short time, the M&E of the S12 building has completed 7/26 floors, equivalent to 27% - ahead of schedule. The project is expected to be handed over to the investor in August 2020. The work is carried out according to the construction standards, strictly inspected and regularly disseminated for labor safety.
One of the high-rise buildings was constructed by HVC Group
S12-HVC Group Building progressed ahead of schedule
Besides the M&E works, promoting the strength of being the leading general contractor of entertainment equipment in Vietnam, HVC Group is also the contractor of constructing fountains, sprinkling floors, low-volume PK1 water walls. floor, MegaMall Trade Center, landscape CT1 and park B2, CT1 and park B2, Division 2 - Lot CT 03, lake landscape number 6; swimming pool at Vinhomes Ocean Park High School and many other items.
In the process of construction, despite many difficulties due to complex design, high aesthetic requirements, high precision, measures to combine many tools and equipment, but with determination, high effort of HVC Group has completed the project on schedule, quality assurance, safety and is highly appreciated by the investor.