At the end of October 2022, HVC's key projects are still executed efficiently, with quality and on schedule
04/11/2022
Over the past time, HVC Group has continuously completed and handed over many important bidding packages for water music, water park, swimming pool, sauna technology, cold snow sauna, etc. That shows HVC's commitment to quality. , construction progress is always guaranteed. In addition, other important projects that the company is implementing also have many new steps.
NovaWorld Phan Thiet Water Park
Information from the construction site, after completing 100% of the engine rooms, last October, HVC Group focused on water treatment, error checking and troubleshooting (if any). In addition, HVC also runs test runs of items with Proslide experts and investors. It is expected that in November, the design and construction bidding package for water filtration and water treatment of tanks in Ocean Kingdom water park (under NovaWorld Phan Thiet) will be accepted and handed over.
King Garden Resort & Villas
With the hot mineral spring swimming pool - onsen, HVC has completed the installation of the system (not including the heatpum) and conducted a full test run including the Jaccuzi massage system as well as the filtration technology. Construction is rushing to complete the remaining items to put into use.
In Thanh Dong - Minh Duc area (including 25 swimming pools): HVC has completed installation of external equipment and filtration system. In addition, the installation of 2 rooms with hot mineral water supply, living up to 25 villas has been 90% completed.
Meanwhile, 18 Kaiwa swimming pools have also completed installation of equipment outside the swimming pool. HVC Group continues to be trusted by the investor, tasked with designing and constructing the swimming pool technology and hot mineral water supply system in the new Thanh Lien - Bich Lien area with the number of 78 villas. Currently, the construction site has completed the construction of swimming pool technology pipelines, external tank water supply, and completed 30 apartments.
Last month, HVC also installed swimming pools and hot mineral water supply for 14 villas in Hong Lien area.
In the coming period, HVC will complete the installation, test run and hand over 25 swimming pools and hot mineral water supply in Thanh Dong - Minh Duc area. Installation and construction of technical rooms of 18 Kaiwa villas. Continue to construct the pool technology system, water supply in Thanh Lien - Bich Lien area of construction contractors ICIC, Truong Sinh, Anh Phat. At the same time, the construction of the water playground has been approved by the investor.
Apec Mandala Wyndham Mui Ne
In this project, HVC has basically completed the entire equipment of swimming pools, villa pools, massage systems and is waiting for handover and trial operation. At the same time, HVC is still coordinating with construction contractors to perfect the equipment in the tank. As previously shared, due to a number of objective factors, the investor delayed the handover of the apartments, leading to the completion of HVC's items being forced to move.
Apec Mandala Sky Villa Hoa Binh
Mr. Vu Tien Khuong (Deputy Project Manager) provided, for the 7-storey building, HVC is constructing a heatpump water supply room, fire protection pump room, pulling fire alarm wires. Conference House: HVC constructs and installs air ducts, FCUs, and water pipes. The infrastructure part is installing fire pipes.
Construction of negative part, installation of pipes
Deploying at the same time building 7 floors and conference house
The Horizon Bay Ha Long
According to the signed contract, HVC will hand over the bidding package to the investor and put it into use on December 23, 2022. Currently, the process of M&E construction has been deployed 1/2 of the volume. Specifically, HVC is constructing water supply and drainage systems, electricity for 261 shophouse villas and townhouses.
HVC is speeding up construction, promising to "finish" on schedule
Vinhomes Dream City
With the 2nd and 3rd phase M&E infrastructure package of nearly 2,400 low-rise apartments, HVC is completing PK2, PK8 and continuing to construct and install light poles, pull power cables for apartments. PK5 audio is also being implemented.
Meanwhile, the M&E M&E general contractor package for 146 villas 20 + 22 Coral subdivision has just received the ground and deployed the raw part for 15%.
Vinhomes Dai An
In this project, HVC has completed the lighting and drainage system of the main road for sales. The construction site said that currently the landscape at the beginning of the N3 road has reached 80%, the crossing positions at PK4 for internal construction have been completed 70%. In addition, the lawn irrigation system is still under construction.
Construction of electricity and water pipes through PK4 . road
Yoko Onsen Quang Hanh
After handing over 70 villas, HVC has perfected the technology of hot and cold sauna for the remaining 100 villas in Zone 1, Zone 2 and Zone 3 subdivisions. It is expected that in November, it will conduct acceptance and acceptance. handing over 53 villas. Others are in the process of commissioning, testing, detecting and fixing errors.
Van Phuc City
With many years of practical experience in the field of design consultancy, construction, installation of water music, fountains..., HVC Group has become a contractor to supply a part of equipment, construction and renovation of music works. water in Van Phuc City.
According to Mr. Pham Van Tac (Project Manager), on September 16, 2022, HVC started dismantling equipment and conducting professional work. As of October 30, HVC has finished installing all water music improvement equipment. It is known that from November 1-7, HVC will operate and test the system.