Progress of construction sites by HVC Group until the end of July 2023
02/08/2023
In the past time, in the context of economic difficulties, but HVC Group (stock code: HVH) is still determined to make efforts, sign and hand over many valuable bidding packages. Besides, HVC also promotes construction in key projects across the country.
King Garden Resort & Villas
In July 2023, HVC handed over to the investor to put into operation and use many items. Specifically: Handing over the water playground; mineral spring swimming pool system; Swimming pool technology system of 31 villas in Hong Lien and Thanh Lien areas and hot mineral water supply for 37 villas.
Swimming pool villas in Hong Lien area, Thanh Lien has been completed
The hot mineral supply system for 37 villas is also handovered
In the next phase, HVC will complete the installation of a swimming pool system and provide hot mineral water for 41 villas in ICIC, Truong Sinh, Son La areas. Deploying a service complex of 4 onsen villas including swimming pool, mineral water jacuzzi. In addition, HVC also carried out the construction of phase 1 of the pipeline system for swimming pools and water supply for 37 villas in Anh Phat area. Continuing to receive the trust of the investor, HVC is in charge of the design and construction of the hot mineral swimming pool of Service 8.
Hot mineral swimming pool Service 8 designed and constructed by HVC
Vinhomes Dream City (Vinhomes Ocean Park 2)
In Coral subdivision, the general contractor for the infrastructure M&E system of 1,137 low-rise apartments was handed over by HVC from February 2023. In which, the handover and inventory of assets in zones 2 and 8 have been completed. Area 5 also completes camera system, lighting, lightning protection, distribution cabinet. Particularly, the system of electric meter cabinets and water meter boxes are being tested and accepted. According to the plan, this general contractor package will be handed over 100% in August.
The handover and counting of assets at the infrastructure M&E general contractor package are about to be completed
In addition, here, HVC is also the general contractor for the completion of M&E for 145 villas 20 + 22. The construction site said that HVC quickly completed this package on June 15. Currently handing over to the investor 62 out of 145 villas. Thus, at this key project, all of HVC's bidding packages have "reached the finish line" successfully.
Out of a total of 145 villas, HVC built 71 villas
The remaining 74 villas are completely completed
|
Currently, HVC has handed over 62 villas
|
Apec Madala Sky Villas Hoa Binh
At the project, HVC is the M&E general contractor that implements the construction of electricity, water, fire protection and air conditioning systems at the 7-storey hotel and functional houses.
The hotel area has completed 95% construction
Mr. Vu Tien Khuong (Deputy Commander) informed that the construction and installation process reached 95%. At this time, HVC is inspecting, repairing and preparing for acceptance and handover.
The service area of the project is almost completed
Electricity, water, fire protection and air conditioning systems are about to be accepted and handed over
The Horizon Bay Ha Long
With the package of construction of water supply and drainage systems, electricity for 261 shophouse villas and townhouses, HVC has implemented 82%. It is expected that in September 2023, HVC will conduct acceptance test, hand over BIM Group to the investor and put it into use.
HVC has implemented 82% of the work of the package
Vinhomes Dai An (Ocean Park 3)
In the past period, HVC Group has completed and handed over many important contracts for M&E and high-end entertainment equipment in Ocean Park 3. At this time, HVC is rushing to deploy at the same time. 2 bidding packages, including: Construction of infrastructure, traffic of M&E part of West Bay subdivision 4 and construction of M&E route for sales.
HVC has accepted the pavement sound ME system and handed over the construction site
Tender package for M&E infrastructure and traffic construction, subdivision 4, West Bay, HVC has implemented 40%. Meanwhile, the M&E construction of the route for sales reached 50%. Both packages are expected to be handed over in December 2023.
Construction and waiting for the M&E system across the road of the sales service route
Yoko Onsen Quang Hanh
At Yoko Onsen Quang Hanh, the sauna and cold sauna system of the entire Zone 1 and Zone 2 areas has been handed over. In Zone 3, HVC handed over 45 villas and put into operation, the remaining 83 apartments are still waiting for acceptance.
Zone 3 has been handed over by HVC the sauna and cold sauna system of 45 villas
L’Aurora Phu Yen
Right after the contract was signed, HVC quickly started construction of the swimming pool model apartment TM 17.1. Mr. Nguyen Tuyen Tuan (Project Manager) said, with the model villas, HVC has completed 80%.
HVC is completing the construction of the model swimming pool
The Global City
After the success of the largest water music project in Southeast Asia, HVC continued to become the M&E infrastructure general contractor for the entire project. Currently, HVC is in the process of waiting for the investor to hand over the site for construction.
SOHO townhouses in The Global City urban area are accelerated construction progress