HVC Group actively deploys key bidding packages across the country

15/06/2024

From the beginning of the year, HVC Group has continuously completed and handed over many important packages at large projects so far. This is the clear evidence of HVC's commitments on the construction progress as well as the project quality. Also, HVC is still actively executing other key bidding packages in Ho Chi Minh City, Phu Yen, Quang Ninh, Phu Tho, Hung Yen...

The Global City

At The Global City - one of HVC's major construction sites, engineers, workers and machines have been working hard to ensure the progress.

Soho subdivision has been constructed by HVC and handed over the M&E infrastructure category.

According to the signed contract, HVC is the general M&E infrastructure contractor of the project with specific tasks: Construction of water supply systems, fire protection, road lighting M&E and low-voltage power supply.

Complete the cast iron pipe system on bridges No. 1, 2, 3, 4 and 5

Previously, HVC has quickly completed and handed over phase 1 in the Soho subdivision to the investor. At the same time, HVC is executing the construction of M&E infrastructure systems on routes D8, D4, N1P, N1R, N1Q, D2 of phase 2 and routes V, N1G, N1H, D2 of phase 3.

HVC constructed underground pipe systems on routes

HVC Group's Construction site command board said that currently, 80% of the routes has been completed.

Vinhomes Dai An

Two general M&E contractor packages at Vinhomes Dai An including infrastructure M&E and West Bay PK4 traffic and the main road M&E for marketplace, have been completed, accepted and handed over to the Management Board for operation.

HVC has handed over the general M&E infrastructure and transportation tender at PK4 West Bay.

In particular, the general M&E infrastructure and traffic package PK4 Tay Bay includes the following main scopes: Installation of sidewalk lighting systems; Construction of electrical cabinet systems and power supply cabinets for apartments; Installation lightning protection system, water supply, security cameras.

The general electrical and mechanical contractor package for the main route serving trades has been put into operation

M&E general contractor package for main route serving trades includes: installation of sidewalk lighting system, installation of electrical cabinets, power cable installation for tree-wrapping LED lighting system. In addition, HVC also constructed lightning protection systems, water supply, and security cameras

HVC is working on renovating games at central park

Currently, HVC is renovating game No. 10 at the Central Park project. Accordingly, HVC has completed the construction of the game water supply underground pipe and been finishing the installation of the filtration-system room and water-game supply system. It is expected to complete by June 20.

Intercon Residences Ha Long Bay

At the Intercon Residences Ha Long Bay, HVC is the general technology contractor for the entire system of swimming pools, Jacuzzis, miniature pools, and fountains.

Row villas' swimming pool is getting ready to be installed by HVC

Recently, HVC has completed the construction of the outer pipes of 47 swimming pools, ornamental tanks, and fountains. Also, HVC is installing engine rooms for the entire system. In the next phase, HVC will complete the installation of equipment for the engine room and tank wall.

HVC has installed the pipes outside the pool of the bay-view villas' swimming pool and
The engine room is also being installed

Vuon Vua Resort & Villas

During this phase, HVC has completed the swimming pool system of The Golden Palm Onsen Swimming Pool, infinity swimming pool, and hot mineral swimming pool at Service restaurant No.6

Infinity swimming pool in Service Restaurant No.6
Hot mineral swimming pool, hot mineral onsen pool in Service Restaurant No.6

Completed the installation of hot mineral swimming pool system, hot mineral jacuzzi, hot mineral water supply to 4 Onsen villas. At the same time, completed the hot mineral supply for 81 villas at the project. In addition, HVC also installed and ran test the swimming pool, jacuzzi, and hot mineral water supply for the 5-star Kim Lien Hoang Gia model villa.

Hot mineral jacuzzi at 4 Onsen villas

With the trust and appreciation from the investor, HVC continues to carry out the construction of 38 villas in the Indochina area with a swimming pool system and natural mineral water.

Hot mineral swimming pool at 4 Onsen villas

Until now at Vuon Vua Resort & Villas, HVC Group has completed the construction of water filtration and supply technology for 186 villas (of which 21 have hot water swimming pool systems); 1 Onsen infinity swimming pool; 1 Onsen hot spring swimming pool; 4 villas heated swimming pools and 24 onsen hot Jacuzzi... In the coming time, the number of swimming pools completed by HVC will keep rising.

Swimming pool for Kim Lien Hoang Gia model apartment

L’Aurora Phu Yen

HVC Group took the role of general technology contractor for the entire swimming pool system (infinity pool, landscape pool, villa swimming pool) at L'Aurora Phu Yen. To this point, HVC has completed about 90% of the work scope and been installing equipment into the tank to operate the system.

Central swimming pool of the project

Supplying water into villas swimming pools to operate and run the system

Also in this project, HVC also provided and installed mechanical and electrical systems, including: electricity, water, fire protection, ventilation and air conditioning systems for TM6 auxiliary area. By mid-June 2024, HVC has implemented about 20% of the work scope.

HVC is constructing and installing the mechanical and electrical system at TM6

VinWoders at Vinhomes Grand Park

HVC Group is the general contractor for the water supply and filtration technology construction at 11 games of the VinWonders Vinhomes Grand Park theme park. Currently, HVC has provided sufficient materials to the construction site, ready to carry out work as soon as the site is ready.

A corner of the project - where HVC will deploy a water supply and filtration technology tender for 11 games

Yoko Onsen Quang Hanh

In this project, HVC Group handed over all sauna and igloo technology for 170 villas and received high praise from investor Sun Group.

The villas are equipped with sauna and igloo technology

Beside the above projects, HVC is still executing many bidding packages on electromechanical and high-end entertainment technology in other localities across the country. With the motto of Prestige - Creativity - Responsibility, HVC has been constantly improving the quality of human resources, investing in modern technologies, and standardizing the operating procedures to deserve the trust of customers & investors