Accelerating progress, many bidding packages of HVC entered the sprint stage
07/08/2022
In addition to the newly signed bidding packages, HVC Group continues to accelerate the progress of key projects in Hung Yen, Quang Ninh, Hoa Binh, Phu Tho, Binh Thuan... Notably, many of HVC's bidding packages are entering the final stage. sprint to hand over the investor to put into operation and use the National Day holiday on September 2.
Vinhomes Dai An
As previously reported, in the largest scale project in Hung Yen, HVC continues to carry out M&E construction of main road infrastructure for sales and technology packages.
News from the construction site reports that, currently, the following items: Outdoor swimming pool, indoor swimming pool salt generation technology, Kid pool water filtration system, filtration system and water supply to the slide of the Mini Water Park and The canvas swimming pool has achieved 80% progress.
Specifically, HVC is installing equipment and pouring filter sand for 2 outdoor swimming pools. Kid pool area and slide water supply are in the process of checking and fixing errors and problems (if any). Due to the new premises, the indoor saltwater tank and the canvas tank are being installed in the engine room. It is expected that HVC will complete the technology bidding packages before September 2 to hand over to the investor and put it into operation.
With the M&E package, HVC also quickly deploys the works to ensure the progress. Accordingly, the water supply and drainage system has been constructed at points through the N2, N4, N7 route. The light-electricity system has completed the temporary parking lot and supplied the lighting system for the N7 route, 30% for the N2 route, and 40% for the N4 route. Overall site HVC received 5% and is under construction 5%.
Vinhomes Dream City
In this project, in addition to the completed bidding packages and handed over to the investor, HVC also constructed the second and third phase of infrastructure M&E system of nearly 2,400 low-rise apartments. Accordingly, the low-voltage pipeline system, apartment water supply and drainage pipes for lines N30, 32, 34, 38, 42, 44, 46 PK2 phase 2 and lines D15, D22 PK8 phase 3 are under construction.
NovaWorld Phan Thiet Water Park
Mr. Nguyen Dai Han (Project Manager) said: “HVC has completed the construction and installation of the water filtration system and water supply for the games of the water park. Currently, we are coordinating with construction to complete installation of water supply surface equipment and commissioning. It is expected that the items will be handed over in early September.”
King Garden Resort & Villa
At this stage, HVC is urgently completing the pipeline system, 2 onsen engine rooms and hot spring swimming pool. It is expected that September 2 will conduct a test run.
In the next phase, HVC will install equipment for 25 villas in Thanh Dong - Hong Lien - Minh Duc and 18 villas in Kaiwa area.
Apec Mandala Wyndham Mui Ne
The project management board informed that the construction site is coordinating the installation and completion of swimming pool equipment and is ready for testing. Previously, HVC expected to put into operation on June 30, but due to a number of objective factors, the investor delayed the delivery of the apartment, leading to the completion of HVC's work being forced to move. Translate.
Apec Mandala Sky Villa Hoa Binh
According to the announcement from the investor, the handover progress of the items will be pushed to the end of the year. Specifically, the fire prevention and fighting work item was accepted at the beginning of November. Meanwhile, the electricity, ventilation, and water supply and drainage systems are expected to be handed over in mid-December, 2022. However, HVC still carried out the work, ensuring the schedule committed to the investor.
Yoko Onsen Quang Hanh
On the supply side of the construction site, HVC has completed the technology of sauna and cold sauna for 105 villas. With the desire to bring the best quality items, HVC is continuing to check, review and correct some details of the saunas. It is expected that the handover work will be divided by the investor in August 2022. Simultaneously, HVC continues to implement phase 2 of the project.
The Horizon Bay Ha Long
Mr. Kieu Van Hai (Commander) shared, HVC received the ground for The Horizon Bay Ha Long project from July 15, 2022. At the moment, HVC is doing the work of placing and waiting for water supply and drainage and electricity. In parallel, the construction and completion of the indoor water supply and drainage system for 261 townhouses and Shophouses is carried out.
With a team of highly qualified and experienced technical personnel, along with good financial capacity, over the years, HVC Group has always been chosen by investors to participate in large-scale projects across the country from design to construction. Supplying materials and equipment to the construction site. That further proves the prestige and capacity of HVC in the field of electromechanical general contractor and high-end entertainment technology in Vietnam.