HVCgroup project progress update at the end of Q3 2026
12/10/2026
Alongside securing new contracts in the fields of MEP general contracting and high-end entertainment equipment, HVC made significant progress in the third quarter of 2026, completing and handing over several major projects, including Phenikaa University and CNCTech Glory. At ongoing construction sites, HVC continued to accelerate construction activities, closely adhering to project schedules and investors' requirements.
Happy Home Trang Cat
At the Happy Home Trang Cat project, HVC continued to accelerate the implementation of its MEP general contracting package across five nine-storey buildings. To date, all MEP provisions and embedded works in these buildings have been completed.
HVC is simultaneously carrying out construction works across all five nine-storey buildings at the project
On site, HVC is focusing on rough-in MEP installations across the five buildings and one basement level, including electrical conduits, cable pulling, HVAC systems, fire protection systems, and water supply and drainage systems. Approximately 30% of the rough-in MEP works have been completed.
Workers installing the fire protection system in the building corridorsMEP systems installed in the corridors, including electrical, water supply and drainage, fire protection, and HVAC systemsConcealed ceiling MEP systems in apartments, including electrical, air conditioning, water supply and drainage, exhaust ventilation, and fire protection systems
CNCTech Dream
According to the Project Management Team, HVC continued construction works at factory buildings No. 22, 23, and 24 during the third quarter.
At factory building No. 22, structural construction works are nearing completion, while fire protection system installation is underway. Meanwhile, structural erection works are continuing at factory buildings No. 23 and 24.
HVC is simultaneously carrying out construction works at factory buildings No. 22, 23, and 24
Sailing Club Residences Ha Long Bay
At this project, HVC is simultaneously implementing several packages, including hotel MEP systems, infrastructure MEP systems, and technology systems for the lazy river and swimming pools.
For the hotel MEP package, approximately 80% of the rough-in installation works have been completed. HVC has also begun installing finishing fixtures and equipment, including lighting fixtures and sanitary ware.
HVC is accelerating the hotel MEP installation package
HVC has completed approximately 80% of the rough-in MEP installation works
Regarding the infrastructure MEP package, HVC has completed underground cable installation, installed electrical distribution cabinets, and finalized electrical connections. The construction team is currently erecting street lighting poles.
Infrastructure cable installation has been completedElectrical distribution cabinet installation is progressing according to scheduleHVC is installing street lighting poles
Meanwhile, HVC is installing equipment in the plant rooms for the lazy river and swimming pool technology systems.
Current construction progress of the lazy river and swimming pool technology systems undertaken by HVC
Vinhomes My Lam
HVC serves as the general contractor for the entire Onsen technology system, covering Onsen pools, Jacuzzi systems, therapeutic steam rooms, saunas, snow rooms, and other specialized facilities. To date, approximately 90% of the infrastructure works and technical tunnel systems have been completed. The plant room works have reached 30% completion, with equipment delivery to the site pending for subsequent installation.
For the sauna system, construction progress has reached approximately 60%, with equipment installation yet to commence.
A view of the Vinhomes My Lam projectHVC carrying out infrastructure rough-in installation worksInspection and acceptance of pipeline and Onsen pool pressure testing
Phenikaa Tower Hoa Lac
During the third quarter, HVC completed rough-in MEP installations in the apartment and corridor areas from the 2nd to the 10th floors.
Construction activities are currently underway from the 11th to the 21st floors, with MEP installations having progressed to the 17th floor.
HVC carrying out MEP installation works at the projectHVC has completed rough-in MEP installations up to the 17th floor
Alongside the rough-in works, HVC has begun installing equipment and fixtures on the show floor, preparing for the next stages of project completion.
Equipment and fixture installation is underway on the building's show floor
Sun Urban City Ha Nam
At Sun Urban City Ha Nam, HVC has completed approximately 70% of the internal stormwater drainage package in Zones 1 and 2.
Meanwhile, the infrastructure MEP package in Zone 2 has also reached approximately 70% completion.
HVC continues to implement the internal stormwater drainage package in Zones 1 and 2Construction works have reached approximately 70% completion
Eurowindow Light City
Along Bac Song Ma Boulevard, HVC has completed 100% of the MEP works within its contracted scope.
In internal Zone 1.2, construction teams are continuing to implement the remaining sections of the infrastructure network.
Inspection and acceptance of cable trenches, conduit installations, and low-voltage warning tapes along Route D18HVC installing lighting poles along internal roads
Crystal Holidays Harbour Van Don
Recently, HVC completed the handover of the all-season swimming pool on the 5th floor of Buildings A and B to the investor.
For the penthouse swimming pools, HVC is currently awaiting site handover to resume construction activities.
The all-season swimming pool has been handed over by HVC to the investor and put into operation
Sonasea Premier Nha Trang
Under the package for the supply and installation of water park technology systems and amusement equipment, HVC has completed the installation of all amusement equipment.
The company is currently finalizing the plant rooms to proceed with the installation of the water supply and filtration systems.
HVC has completed the installation of the water park amusement equipment
All remaining works are expected to be completed by the end of October 2026, paving the way for final inspection, acceptance, and handover.
Vuon Vua Resort & Villa
During the third quarter, HVC completed the installation of the technical plant room serving the swimming pool and Onsen Jacuzzi at villas BT33.01-02.
The company also handed over the technical plant rooms for the swimming pool, Onsen Jacuzzi, and fish pond at villas BT33.01-02 to the investor.
HVC carrying out embedded underground pipe installations for the swimming pool infrastructureHVC has completed and handed over the technical plant room serving the swimming pool and Onsen Jacuzzi at BT33.01-02
In the new De Lien Kim Hai area, HVC is installing and completing the swimming pool plant rooms at BT28.20-21 and BT28.26-27, serving 12 villas.
In addition, HVC is carrying out embedded underground piping works for swimming pool systems, mineral water supply, and domestic water supply to individual villas.
In the Japanese Village area, HVC is installing embedded underground infrastructure pipelines for villas BT35.01 and BT35.02.
Alluvia City
At the Alluvia Onsen subdivision, HVC is responsible for the construction and completion of the power supply and extra-low-voltage (ELV) infrastructure systems.
To date, material approvals, procurement arrangements, and shop drawings have been substantially completed.
HVC is currently awaiting site handover from the investor to commence construction works.
A view of the Alluvia Onsen subdivision, where HVC is responsible for the infrastructure MEP works.