In line with the pace of urgency "the day of continuous construction, the night of continuous bright light" of Vinhomes Ocean Park project (VinCity Gia Lam), HVC Technology and Investment Joint Stock Company (HVC Group) is rushing to complete work in accordance with the signed contract including electrical and mechanical infrastructure, building and electrical engineering and many other items.
Mechanical and electrical infrastructure: completing over 80% of the total work
Receiving the support and creating favorable conditions from the investor, immediately after receiving the premises, HVC Group carried out the transportation of machinery, equipment and materials, mobilized high-tech personnel to quickly serve the project. . Up to now, many items have been completed as in road 49, N3 ...; completing 100% of raw materials for auxiliary buildings; many lines are conducting trial run, completing 80% or waiting for ground from investors to be ready for construction
The Gia Lam Vinhomes Ocean Park, is busy with activities day-night
HVC Group is in tune with the progress of the project with many parts completed
General contractor of electrical and mechanical building: ensuring on-time schedule
The general M&E contractor of the building is being constructed to ensure the progress with the completion of 30% of raw materials. It is expected that the entire work will be handed over by HVC Group at the end of December 2019 in accordance with the commitment to the investor.
According to Mr. Nguyen Quoc Bao, the commander of HVC Group at the project: With the experience of many mechanical and electrical construction projects, the work we do is in a rolling form, completed floor by floor technically and clearly . Despite the harsh weather, the technical staff and workers always work in a spirit of seriousness and highest responsibility.
Mr. Bao also said, “In addition to ensuring the quality and progress of the project, the work safety is always placed on top of HVC Group. We maintain a safe meeting at the beginning of the day to remind employees to implement the construction techniques properly; how to identify hazards and unsafe situations that can occur in labor and how to prevent them. ”
Tool Box - the first safe meeting activity before every shift is fully and professionally implemented by HVC Group at Vin City and other projects nationwide.
A corner of office and warehouse of HVC Group at Vin City Gia Lam site always shows seriousness and professionalism.
HVC Group is implementing the schedule of all works in the package including: Electricity, Fire protection, Air conditioning, Water supply and drainage
Vinhomes Ocean Park Gia Lam is a civilized and modern city that is planned to be a Singapore-class city. Vinhomes Gia Lam is expected to be divided into 2 subdivisions: High-rise zone and Low-rise zone. Low-rise areas include various types of adjacent villas, garden houses, duplex villas, single villas, Shophouse. High-rise zone includes 66 buildings with a height of 23 -26 floors, with apartments of 35-85m2, from 1 to 3 bedrooms, fully meeting the needs of all customers.